Federal Power Commission v. Sierra Pacific Power Co., 350 U.S. 348 (1956), is a United States Supreme Court case in which the Court interpreted the Federal Power Act (FPA) as permitting the Federal Power Commission (FPC) to modify a rate specified in a contract between an electric utility and distribution company only upon a finding that the contract rate is unlawful because it adversely affects the public interest. Sierra Pacific and its companion case United Gas Pipe Line Co. v. Mobile Gas Service Corp. established the Mobile-Sierra doctrine, which holds that an electricity or natural gas supply rate established resulting from a freely negotiated contract is presumed to be "just and reasonable" and thus acceptable under the FPA or Natural Gas Act (NGA).

AttributesValues
rdf:type
rdfs:label
  • Federal Power Commission v. Sierra Pacific Power Co. (en)
rdfs:comment
  • Federal Power Commission v. Sierra Pacific Power Co., 350 U.S. 348 (1956), is a United States Supreme Court case in which the Court interpreted the Federal Power Act (FPA) as permitting the Federal Power Commission (FPC) to modify a rate specified in a contract between an electric utility and distribution company only upon a finding that the contract rate is unlawful because it adversely affects the public interest. Sierra Pacific and its companion case United Gas Pipe Line Co. v. Mobile Gas Service Corp. established the Mobile-Sierra doctrine, which holds that an electricity or natural gas supply rate established resulting from a freely negotiated contract is presumed to be "just and reasonable" and thus acceptable under the FPA or Natural Gas Act (NGA). (en)
foaf:name
  • (en)
  • Federal Power Commission v. Sierra Pacific Power Co. (en)
foaf:depiction
  • http://commons.wikimedia.org/wiki/Special:FilePath/Shasta_Dam.jpg
dcterms:subject
Wikipage page ID
Wikipage revision ID
Link from a Wikipage to another Wikipage
Link from a Wikipage to an external page
sameAs
Subsequent
  • . (en)
dbp:wikiPageUsesTemplate
thumbnail
JoinMajority
  • unanimous (en)
LawsApplied
  • Federal Power Act, et seq. (en)
oyez
ParallelCitations
Prior
USPage
USVol
ArgueDate
ArgueYear
case
  • Federal Power Commission v. Sierra Pacific Power Co., (en)
courtlistener
DecideDate
DecideYear
findlaw
fullname
  • Federal Power Commission v. Sierra Pacific Power Co. (en)
Holding
  • A contract rate filed under the Federal Power Act is unlawful only if the rate is so low as to affect the public interest by being unduly discriminatory, excessively burdensome to consumers, or a threat to continued service. (en)
justia
Litigants
  • Federal Power Commission v. Sierra Pacific Power Co. (en)
majority
  • Harlan (en)
loc
has abstract
  • Federal Power Commission v. Sierra Pacific Power Co., 350 U.S. 348 (1956), is a United States Supreme Court case in which the Court interpreted the Federal Power Act (FPA) as permitting the Federal Power Commission (FPC) to modify a rate specified in a contract between an electric utility and distribution company only upon a finding that the contract rate is unlawful because it adversely affects the public interest. Sierra Pacific and its companion case United Gas Pipe Line Co. v. Mobile Gas Service Corp. established the Mobile-Sierra doctrine, which holds that an electricity or natural gas supply rate established resulting from a freely negotiated contract is presumed to be "just and reasonable" and thus acceptable under the FPA or Natural Gas Act (NGA). (en)
googlescholar
prov:wasDerivedFrom
Faceted Search & Find service v1.17_git139 as of Feb 29 2024


Alternative Linked Data Documents: ODE     Content Formats:   [cxml] [csv]     RDF   [text] [turtle] [ld+json] [rdf+json] [rdf+xml]     ODATA   [atom+xml] [odata+json]     Microdata   [microdata+json] [html]    About   
This material is Open Knowledge   W3C Semantic Web Technology [RDF Data] Valid XHTML + RDFa
OpenLink Virtuoso version 08.03.3330 as of Mar 19 2024, on Linux (x86_64-generic-linux-glibc212), Single-Server Edition (378 GB total memory, 59 GB memory in use)
Data on this page belongs to its respective rights holders.
Virtuoso Faceted Browser Copyright © 2009-2024 OpenLink Software