A hammock activity (also hammock task) is a schedule or project planning term for a grouping of tasks that "hang" between two end dates it is tied to. A hammock activity can group tasks that are not related in the hierarchical sense of a Work Breakdown Structure, or are not related in a logical sense of a task dependency, where one task must wait for another. Usage includes:

AttributesValues
rdf:type
rdfs:label
  • Hammock activity (en)
  • Hammock (pt)
rdfs:comment
  • A hammock activity (also hammock task) is a schedule or project planning term for a grouping of tasks that "hang" between two end dates it is tied to. A hammock activity can group tasks that are not related in the hierarchical sense of a Work Breakdown Structure, or are not related in a logical sense of a task dependency, where one task must wait for another. Usage includes: (en)
  • Uma tarefa do tipo hammock em um cronograma é uma tarefa que tem o seu início e duração não determinados previamente, mas exclusivamente dependentes do início ou término de outras tarefas. Com isto, a quantidade de recursos necessários para execução da tarefa deve ser determinado com base no início e término de outras atividade, e não é conhecido antes do início da elaboração do cronograma. O PMI define no Practice Stanard of Scheduling como sinônimo de tarefas-resumo. (pt)
dcterms:subject
Wikipage page ID
Wikipage revision ID
Link from a Wikipage to another Wikipage
Link from a Wikipage to an external page
sameAs
dbp:wikiPageUsesTemplate
has abstract
  • A hammock activity (also hammock task) is a schedule or project planning term for a grouping of tasks that "hang" between two end dates it is tied to. A hammock activity can group tasks that are not related in the hierarchical sense of a Work Breakdown Structure, or are not related in a logical sense of a task dependency, where one task must wait for another. Usage includes: * Group dissimilar activities that lead to an overall capability, such as preparations under a summary label, e.g. "vacation preparation"; * Group unrelated items for the purpose of a summary such as a calendar-based reporting period, e.g. "First-quarter plans"; * Group ongoing or overhead activities that run the length of an effort, e.g. "project management". The duration of the hammock activity (the size of the hammock) may also be set by the subtasks within it, so that the abstract grouping has a start date of the earliest of any of the subtasks and the finish date is the latest of any of the contents. A hammock activity is regarded as a form of Summary activity that is similar to a Level of Effort (LOE) activity. Use of hammock activities is also a way to simplify the difficulties of performing Work Breakdown Structure decomposition to low levels. Also, hammock tasks can represent any group of tasks in the Integrated Master Schedule (IMS) regardless of their physical location or parent Work Breakdown Structure (WBS) element. (en)
  • Uma tarefa do tipo hammock em um cronograma é uma tarefa que tem o seu início e duração não determinados previamente, mas exclusivamente dependentes do início ou término de outras tarefas. Com isto, a quantidade de recursos necessários para execução da tarefa deve ser determinado com base no início e término de outras atividade, e não é conhecido antes do início da elaboração do cronograma. O PMI define no Practice Stanard of Scheduling como sinônimo de tarefas-resumo. Exemplos típicos de tarefas Hammock são atividades de gerenciamento do projeto ou guarda-noturna de um canteiro de obras, pois a sua execução não é conhecida enquanto o projeto não estiver completamente planejado. (pt)
gold:hypernym
prov:wasDerivedFrom
page length (characters) of wiki page
foaf:isPrimaryTopicOf
is Link from a Wikipage to another Wikipage of
is foaf:primaryTopic of
Faceted Search & Find service v1.17_git139 as of Feb 29 2024


Alternative Linked Data Documents: ODE     Content Formats:   [cxml] [csv]     RDF   [text] [turtle] [ld+json] [rdf+json] [rdf+xml]     ODATA   [atom+xml] [odata+json]     Microdata   [microdata+json] [html]    About   
This material is Open Knowledge   W3C Semantic Web Technology [RDF Data] Valid XHTML + RDFa
OpenLink Virtuoso version 08.03.3330 as of Mar 19 2024, on Linux (x86_64-generic-linux-glibc212), Single-Server Edition (378 GB total memory, 53 GB memory in use)
Data on this page belongs to its respective rights holders.
Virtuoso Faceted Browser Copyright © 2009-2024 OpenLink Software