. "The Amaranth Wind Farm, also known as the Melancthon EcoPower Centre, is a 199.5 megawatt (MW) wind farm in Amaranth and Melancthon Township, near Shelburne, Ontario. The centre is owned and operated by TransAlta and at the time of opening, was Canada's largest wind energy installation. Construction of the Melancthon EcoPower Centre began with the 67.5 MW Phase I in 2005 and achieved commercial operation in March 2006. Construction of the 132 MW Phase II of the project began in 2007 and achieved full commercial operation in November 2008."@en . . . . "20234433"^^ . . . . . "Amaranth Wind Farm"@en . . "3708"^^ . . . "2006-03-04"^^ . . . . . . . . . "2005"^^ . "Amaranth and Melancthon Township, near Shelburne, Ontario"@en . . . . . "Amaranth Wind Farm"@en . . . . . . "44.1001 -80.2709" . . . . . . "Wind farm in Melancthon"@en . . . "Canada"@en . . "POINT(-80.270896911621 44.100101470947)"^^ . . "2005" . "44.10010147094727"^^ . . . "199.5"^^ . . . . . "2005"^^ . . . . . . "2006"^^ . "2006-03-04"^^ . . . "199500000.0"^^ . "The Amaranth Wind Farm, also known as the Melancthon EcoPower Centre, is a 199.5 megawatt (MW) wind farm in Amaranth and Melancthon Township, near Shelburne, Ontario. The centre is owned and operated by TransAlta and at the time of opening, was Canada's largest wind energy installation. Construction of the Melancthon EcoPower Centre began with the 67.5 MW Phase I in 2005 and achieved commercial operation in March 2006. Construction of the 132 MW Phase II of the project began in 2007 and achieved full commercial operation in November 2008."@en . "Operational"@en . "-80.27089691162109"^^ . "Operational" . "Amaranth Wind Farm"@en . . "956898643"^^ . . .